Omega Warrington
Major Development Project:
Omega is a £1bn, 233-hectare mixed-use development site on part of the former Burtonwood Airbase in Warrington, Cheshire, situated off Junction 8 of the M62. As a joint venture regeneration project, Omega provides a range of affordable houses, and community shopping and leisure facilities. The development is set within 35-acre areas of landscaping, woodland, parkland and wildlife areas.
Our dedication, commitment, and mutual respect between client and contractor resulted in repeat and ongoing work on the project:
- Bulk earthworks
- Remediation
- Site clearance
- Crushing and recycling materials
- Demolition
- Full highway specification road construction
- Directional drilling under the M62
- Local employment and extensive local supplier partners established
- Drainage including swales, ponds, lagoons, attenuation ponds and SUDS
- Foul pumping and foul water drainage systems
- Construction of Primary and Sub Stations
- Soft and hard landscaping
- Ecology – translocation of Bee Orchids, pond life and fish
- On-site services including mains electricity, gas, water and telecommunications
Our Involvement as Principal Contractor:
D Morgan Plc has had a continuous presence on the Omega Development, being the key delivery partner of choice for the various Clients, and for Miller Developments, the land owner. WSP undertook the design for the project, and it was best decided to amend the contract to Design & Build. D Morgan Plc collaborated with WSP to deliver the design, where we accepted full design responsibility (see table, below).
We were approached in January 2008 to demolish the existing World War II aircraft hangers and runways, and to recycle the existing hard standings. From this early involvement we developed a strong working relationship with the Client and commenced the infrastructure works to the north of the site on various plots adjacent to the M62. Once the north plots had been developed we commenced works to the south of the development, continuing ground remediation, construction of spine roads and extensive hard and soft landscaping.
From our extensive involvement in the overall development plan, we were approached by private developers and have completed their individual plot infrastructure requirements ranging from extensive warehousing through to housing developments.
In addition we are responsible for the completion of the realignment of the slip roads and roundabout to M62 Junction 8 for Balfour Beatty through the SCAPE Framework.
Project Timeline:
CONTRACT NAME
North Hanger Demolition
North Phase 1 – Lockheed Road
ASDA Earthworks
North Phase 2 – Lockheed Road
Travis Perkins Earthworks
South Phase 1 – Skyline Drive
South Phase 2 – Skyline Drive
Hermes Lorry Park
Barrowhall Primary School
South Phase 3 – Sophia Drive
Domino
M62 J8
Olympus Access Works
Seller’s Works
Green Heart Works
Skyline Drive Roundabout
Burtonwood Road Widening
START DATE
January 2008
October 2012
September 2013
September 2013
January 2014
September 2014
September 2014
August 2015
September 2015
September 2015
October 2016
January 2017
October 2017
December 2017
March 2018
March 2018
March 2018